In healthcare, ventilation works cannot simply be booked in for next week. Theatres, wards and treatment areas have to stay safe and operational, shutdowns must be agreed with clinical teams, and funding often has to be secured months in advance. Estates and facilities teams who know a unit needs attention are not always sure how long the process takes or when they need to start. At Building Ventilation Solutions we have refurbished air handling units for NHS trusts and private healthcare providers across the UK. This guide sets out how a typical healthcare ventilation project runs and why early planning makes such a difference.

Ageing plant in healthcare estates

Many NHS buildings date from between 1960 and 1990, and their original ventilation plant was typically designed for a working life of 20 to 25 years. As a result, a large proportion of healthcare air handling units are now running well beyond their intended life. HTM 03-01 Part B applies to all systems regardless of age, so older units are still expected to be maintained and verified against current requirements. Our article on hospital HVAC refurbishment and HTM 03-01 compliance covers this in more detail.

How a healthcare ventilation project runs

Stage 1: Enquiry and initial discussion

You get in touch with details of the plant and the issues you are seeing. We aim to respond within one working day.

Stage 2: Validation survey

Our engineers carry out an AHU validation and ventilation survey covering air change rates, pressure differentials, filter condition and temperature, along with the condition of fans, coils, casings and controls. You receive a report with prioritised recommendations.

Stage 3: Costed options and approval

We set out costed options, from targeted repairs to full refurbishment or new plant. With the NHS financial year running from April to March, having a survey and costed report ready early makes it much easier to secure a place in the next capital programme.

Stage 4: Shutdown planning

Planned downtime is agreed in advance with estates and clinical teams, and works are phased into shutdown windows so ventilation is never fully lost to critical areas. Our rule is simple: no disruption without prior agreement.

Stage 5: Procurement and manufacture

EC fans, coils, controls and bespoke components such as custom heat exchangers are ordered and manufactured. Bespoke items take time, and a complete new AHU can take three to six months to procure, which is why this stage often drives the overall programme.

Stage 6: Works on site

The works are carried out in agreed phases, coordinated closely with site teams so that surrounding departments keep running.

Stage 7: Commissioning, validation and records

Airflow performance is validated after the works and a commissioning record is issued for your estates files, supporting your ongoing compliance.

As with most AHU projects, the time on site is often the shortest part of the process. The survey, approval, shutdown planning and procurement stages are where time is needed, so the earlier you start, the more control you have over when works take place.

BVS healthcare case studies

At Salisbury Hospital, the supply and extract AHUs still had their original belt driven fans and ageing LPHW coils, and could not deliver the increase in airflow the hospital needed. BVS fitted high efficiency EC plug fans, new frost and main heating coils sized for the higher air volume and new stainless steel filter sliders, raising supply airflow from 1.1 m³/s to 1.7 m³/s with no disruption to hospital operations. See the Salisbury Hospital AHU refurbishment case study.

For a private hospital in Bath, we refurbished the air handling unit serving the operating theatres. The old belt driven fans were replaced with Ziehl-Abegg EC supply and extract fans, the unit was reconfigured with new fan bulkheads, and we designed, manufactured and fitted a custom cubic heat exchanger. The works were delivered on time with minimal disruption to day to day operations. See the Bath private hospital AHU refurbishment case study.

At NHS Hammersmith and Fulham, a targeted light refurbishment within a live healthcare facility covered fan drives, filters, coil cleaning, corrosion treatment and bathroom extract fan repairs, extending the life of the plant without a full replacement. See the NHS Hammersmith AHU refurbishment case study.

Tips for estates and facilities teams

  • Survey ageing plant before problems become urgent, so you can plan rather than react
  • Align your survey and costed report with your capital planning cycle
  • Identify likely shutdown windows early and involve clinical teams from the start
  • Allow time for procurement, particularly for bespoke components or new units
  • Keep commissioning and validation records together to support HTM 03-01 compliance

Arrange a healthcare ventilation survey

Planning early is the best way to keep clinical areas running, control capital spend and stay on top of compliance. With over 40 years of experience, BVS supports NHS trusts and private healthcare providers from survey through to commissioning. Contact the BVS team to arrange a validation survey, or explore our hospital ventilation services to find out more.

Engineer Insights

Technical guidance from real AHU projects

Occasional updates covering refurbishment strategy, energy reduction, fan upgrades, controls, and HVAC project guidance.